The short answer
- For most U.S. homes, data centers probably have not raised electric bills yet. The clear exception so far is PJM, a 13-state grid.
- Since July 1, 2026, Florida law says utility rate plans must make a data center that needs 50 megawatts or more pay its own full cost of service.
- The law covers FPL, Duke Energy Florida, Tampa Electric and Florida Public Utilities. It skips city-owned utilities and co-ops.
- A city or county moratorium pauses permits and zoning. It does not set electric rates.
In this guide
Data centers can raise your electric bill, but for most U.S. homes they probably have not yet. In Florida, a 2026 law tells big data centers to pay their own power costs, and it skips city-owned utilities and co-ops.
Rules and filings here were checked Nov. 24, 2026.
Home electricity prices rose 27% from 2021 to 2025. Most of that was inflation, a USAFacts review found in August. Data centers were unlikely to be a large cause across the country, it said.
The exception is PJM, the grid operator for 13 mid-Atlantic and Midwest states and Washington, D.C. Its market monitor tied about $6.3 billion of a $16.4 billion power-supply auction to data centers, USAFacts reported.
In Tampa, the City Council voted to send a pause on new data centers to public hearings, Tampa Bay 28 reported Nov. 23. A federal order that cites growth in data centers is keeping an Orlando coal unit available through Nov. 30.

Will data centers raise electric bills in Florida?
Florida's law is written to stop that. Section 366.043 of the Florida Statutes took effect July 1, 2026.
It covers any customer that needs 50 megawatts or more at one site. That is about what 30,000 to 50,000 homes draw, according to PolitiFact.
Each utility's rate plan must "reasonably ensure" that such a customer pays "its own full cost of service." That includes the hookup, plus any new power lines and power plants built for it.
None of the giant AI data centers proposed for Florida had opened as of August, the same report said.
Which utilities the law covers, and which it skips
The law covers four utilities that the Public Service Commission, or PSC, regulates. They are Florida Power & Light, Duke Energy Florida, Tampa Electric and Florida Public Utilities.
They serve about 75% of the state's population, according to PolitiFact.
It skips rural co-ops and city-owned utilities such as JEA in Jacksonville, OUC in Orlando and Gainesville Regional Utilities. Their own local boards set their pricing rules.
Each covered utility had to file a data-center rate plan by Oct. 1.
| Your utility | Where its plan stands |
|---|---|
| Duke Energy Florida | Rejected Nov. 3 in a unanimous vote. It left out some customers the law covers. Duke has to file a new plan. |
| FPL | Says its current rates already comply. The PSC still has to review that. |
| Tampa Electric | Filed. It says it has no large-load customers yet and expects a decision late this year or early next year. |
What can still raise your bill
When fuel costs rise, utilities pass them to customers. The law does not cap those charges, even if a data center pushes up demand in the region, PolitiFact reported.
The law lists tools such as upfront guarantees and minimum charges, but it does not require utilities to use them.
It "directs a process, not a result," said Mark McNees, a Florida State University professor who researches how AI data centers affect consumers.
Tired of rates you can't control? Solar and a battery let some Florida homeowners buy less power from the utility. Run your own numbers in the solar savings calculator
Does a city moratorium change your electric bill?
A moratorium pauses permits and zoning for new data centers, not electric rates.
Hillsborough County's staff named power costs for other customers as a concern. Their report proposed no rate rules, because the PSC regulates rates, Tampa Bay 28 reported.
Tampa's vote does not start a pause. Hillsborough commissioners put off their own one-year pause on Nov. 10. Two Jacksonville City Council members have filed one there, Jacksonville Today reported.
What to do now
Find your utility's name on your bill. If it is FPL, Duke, Tampa Electric or Florida Public Utilities, the state law applies to it. If it is a city utility or a co-op, ask its board how it plans to bill data centers.
There is nothing to do about your bill yet, because these pieces are still undecided:
- Duke's new plan, and the PSC's reviews of the FPL and Tampa Electric filings.
- A state study of data centers' cost and rate impacts, due July 1, 2027.
- A U.S. Senate bill that would make data centers pay for the energy they use. Senators voted 73-25 on Nov. 9 to take it up, the Associated Press reported.
Solar and batteries will not fix data-center costs. They are one way some homeowners depend less on utility rates. Our net metering guide shows how solar credits appear on a bill, and solar battery storage in Tampa covers backup power.
Sources checked
Sources reviewed Nov. 24, 2026.
- Florida Statutes s. 366.043, Large load tariffs for public electric utilities (2026)
- Florida Senate: CS/CS/SB 484 (2026), enrolled text, ch. 2026-65
- Florida Senate: CS/CS/SB 484 bill history
- Florida Statutes s. 366.02, Definitions (2026)
- USAFacts: Are AI data centers driving up your electric bill? (Aug. 11, 2026)
- Industrial Info Resources: Data centers create about US$6.3 billion in electric costs for PJM customers (July 17, 2026)
- E&E News: What AI data centers do — and don't do — to electricity prices (March 19, 2026)
- PolitiFact via WUSF: Donalds says new law will prevent electric bill hikes from data centers. That's not guaranteed. (Aug. 11, 2026)
- WUSF / News Service of Florida: Regulators reject Duke's data center rate structure (Nov. 4, 2026)
- Environment+Energy Leader: Florida Rejects Duke's Large-Load Tariff (Nov. 6, 2026)
- Spectrum Bay News 9: Florida regulators reject Duke Energy data center cost plan (Nov. 10, 2026)
- WUSF: FPL tells regulators rate structure complies with data center law (Oct. 4, 2026)
- Spectrum Bay News 9: Tampa Electric files plan to protect customers from data center costs (Oct. 1, 2026)
- FOX 13 Tampa Bay: TECO files state plan to protect power customers from data centers (Oct. 2, 2026)
- Tampa Bay 28: Tampa moves toward possible data center moratorium as Hillsborough County weighs its own rules (Nov. 23, 2026)
- WUSF: Hillsborough delays a data center moratorium vote (Nov. 13, 2026)
- Jacksonville Today: 1-year data center moratorium proposed for Jacksonville (Nov. 19, 2026)
- U.S. Department of Energy: Order No. 202-26-42, Stanton Energy Center (Sept. 1, 2026)
- Associated Press via OPB: Senate advances sweeping energy legislation (Nov. 10, 2026)